Hello Support,
Problem:
some jira users have has mistakenly tracked time to an issue in the wrong project A (=IGLU).
Solution:
To solve the problem the tracked time has been moved from the wrong project A(=IGLU) to the correct project B(=ISINT).
The major problem is now:
By moving a tracked time from project A to project B the original account will be keeped even the account doesn’t exist in project B. There is no possibility to change the account to while moving the time to the other project.
This could cause problems with the accounting of the projects, and more work because we have to open the periods again.
Idea:
Please insert the Account field to the "Move Worklog" dialog so users can change the Account if needed while moving the time to another project.
Tempo Products | Tempo Timesheets |
Tempo Platform | Cloud, On-Premise |