I am trying to configure shared resources among 2 teams where each team member has their explicit FTE commitment for each of the teams they are members of.
Team X has 6 members, 2 @ 100% commitment and 4 @ 10% commitment which I expect to equal 2.4 FTE as the total team available capacity.
The same 4 people with 10% commitment in Team X are configured with 90% commitment in Team Y plus 1 additional team member @ 100%, so the Team should have a total of 4.6 FTE available capacity.
However, when I go to team Capacity I see 6 full FTE for Team X and 5 FTE for Team Y, ignoring completely what I configured in commitment.
The request is to see the above partial FTE commitments reflected in Team Capacity views and other relevant reports.
Tempo Products | Tempo Planner |
Tempo Platform | Cloud |
Hi, I also agree that this feature is essential to calculate the actual capacity of teams sharing the same sources in different ratios. Please implement urgently and in the short term, otherwise there is no point in planning with the teams!!!
Hi , I agree that this is must have feature in order to calculate the real capacity of teams that share the same sources on different ratios.