Currently the Folio traffic lights for days ehind always show the linear expected progress, which I don't believe is useful in reality as I'm yet to see a project exxecuting in linear progress from start until the end. Usualy we plan how the project costs/progress will be done in the Cost>Planned.
What we need is the traffic light report for the schedule performance to show how we compare against the plan, not against the linear schedule.