Currently, it is possible to see original estimate of a task when registering time - and set remaining effort.
However, when you cannot see total time registered on the issue, the original estimate is pretty useless. You need to be able to see:
Original estimate
Total time spent
And then the "active" fields:
Time entry
Remaining effort
Our devs cannot easily see if they're within the previously given estimate for a task.
Tempo Products | Tempo Timesheets |
Tempo Platform | Cloud |
Total time spent might be nice to have "me" separate from "everyone else" too - eg:
Remaining Estimate: [ field ]
Original Estimate: 6h
Total Time Spent: 4h (3.5h mine)