We face an issue with baseline and folio re-schedule.
When we reschedule a folio for a given baseline, all the baseline have their start date and end date changed.
So looking to an old baseline, we don’t have the cost that were initialy planned outside the new dates of the folio.
This is a major issue, it makes it very difficult to use baselines.
The start and end date should be part of each baseline to prevent this issue.